Central Street Bridge over Pemigewasset River
Central Street Bridge Construction Schedule
Central Street Bridge Pictures
State Project No. 13573 - Bridge No. 113/064
The bridge was built in 1928 and is considered eligible for the National Register of Historic Places according to the latest NHDOT Bridge Inspection Report dated 5/19/2000. It was given a historic rating of 18 in the NHDOT-NHDHR historic bridge survey in 1982. When the bridge was built in 1928 a concrete cap was added to the stone abutment on the Bristol side and the concrete abutment was built on the New Hampton side. Significant repairs were done to the superstructure in 1975 and a new backwall was added to the concrete abutment.
S E A Consultants Inc. (SEA) had a meeting with the Towns of Bristol and New Hampton on June 20th at the bridge. Representatives from the Towns’ Board of Selectmen, Historic Societies, and Conservation Commissions were present at the meeting. The consensus of the meeting was that the bridge should be replaced rather than repaired. The main reasons for this decision include:
The width of the current bridge is 18 feet. Current AASHTO standards recommend two travel lanes of 10 feet with 2 foot shoulders for an overall width of 24 feet. This is a safety concern for both Towns. Two cars can pass if they go slowly. It is more difficult for a larger truck and car to pass and impossible for a highway department truck and car to pass at the same time. The bridge length of 245 feet makes this minimal width an even greater concern. THE BRIDGE IS JUST NOT SAFE!!!
- The hydraulic issues for this bridge are also important. The bridge currently has a gate on either side of the bridge to keep vehicles from crossing the bridge when it is under water. The S E A Elevation (below) shows the level of the 50-year storm. The plan also shows where the 50-year storm is on either side of the bridge. Flood water backs up from the Franklin Falls dam causing the high levels of water.
- The bridge was rehabilitated in 1975 and is now in need of even more extensive rehabilitation. Long term maintenance costs will be considerably less for a new structure. Based on past experience, S E A feels that the cost to rehabilitate the bridge would be as much as or possibly even more than the cost of a new structure.
- The current alignment of the bridge and its approaches does not meet current AASHTO or NHDOT criteria. The road dips considerably just before the bridge on the Bristol side. Cars practically slam down onto the deck of the bridge after coming down Central Street from Bristol.
At the January 10, 2002 Cultural Resources Meeting S E A asked what would be required if the bridge were to be replaced rather than repaired. S E A would like to know if there would be any additional requirements besides the following:
- Replacing the structure would be considered an adverse effect to a historical resource by the Advisory Council on Historic Preservation (ACHP). An MOA (Memorandum of Agreement) would be required. NHDHR, NHDOT, and the US Army Corps of Engineers would draft the Memorandum. Other consulting parties might include the Historical Societies from the Towns of Bristol and New Hampton. The MOA will need to be approved by the ACHP.
- HAER (Historic American Engineering Record) – documentation would be required including a historic survey, an actual survey or measured drawings and black & white archival photos. The cost of HAER documentation could range from $10,000 to $12,000.
- If the existing bridge is replaced with a wider bridge wider abutments would be required. If these abutments went outside the footprint of the existing abutments, archeological resources may be disturbed. The first phase of an archeological study could cost from $6,000 to $10,000. A full recovery of the area would cost between $40,000 and $100,000.
Estimated Construction Schedule
August 2007
Close roadway, set-up detour, begin construction
August / September 2007
Remove existing bridge
September to December 2007
New Hampton abutment: remove existing and construct new
November 2007
Begin earthwork at New Hampton approach
December to May 2008
Bristol abutment: remove existing and construct new
April 2008
Begin earthwork at Bristol approach
April to June 2008
Construct temporary work trestle and temporary piers in river
June to July 2008
Erect steel girders
July 2008
Remove temporary piers from river
July to September 2008
Cast concrete bridge deck and complete the superstructure
September 2008
Remove temporary work trestle from river
September to November 2008
Complete roadway approach work
November 2008
Remove detour and open roadway to traffic
State Funding Schedule (80% of total costs – design and construction)
1) Eligible to receive 100% of design costs upon NHDOT approval of Final Design
2) After July 1, 2007: Eligible to receive 50% of construction funding upon NHDOT approval of contractor’s construction bid
3) After construction has been complete and approved by NHDOT eligible to receive remaining 50% of construction funding